DiscoverCompany Interviews
Company Interviews
Claim Ownership

Company Interviews

Author: Crux Investor

Subscribed: 177Played: 40,392
Share

Description

An insight into junior mining and opportunities to invest.

Company Interviews, a Crux Investor show, exists to cut through the jargon, bias and bluster.

Matthew Gordon, and guest host Merlin Marr-Johnson hone in on the important factors that indicate a company's strong footing for growth and success.
3850 Episodes
Reverse
Interview with Layton Croft, President & CEO of Carolina Rush Corp.Our previous interview: https://www.cruxinvestor.com/posts/carolina-rush-tsxvrush-first-drill-confirmation-of-copper-gold-porphyry-system-at-brewer-10871Recording date: 19th November 2026Carolina Rush Corp. (TSXV:RUSH) has regained 100% ownership of the Brewer gold-copper project in South Carolina after OceanaGold withdrew from an earn-in agreement in September 2026. OceanaGold, whose Haile Gold Mine lies 15 km from Brewer, had committed to an 80/20 structure focused on the deep porphyry target and spent about US$2 million, drilling three deep holes for more than 2,500 m in 2026 CEO Layton Croft said the partner left because the porphyry is early stage and its priorities sit with advanced projects, and he noted that full ownership removes the cap the 80/20 split placed on shareholder upside. Carolina Rush keeps all core and data.The asset has two value paths. The first is near-surface gold. The 2025 NI 43-101 maiden resource contains about 540,000 oz Au: 192,000 oz indicated at 0.97 g/t, 210,000 oz inferred at 0.74 g/t, and 139,000 oz of inferred backfill at 0.36 g/t, which the company treats as theoretical pending metallurgy. The resource lies within about 175 m of surface. Croft is targeting 1 million oz or more from 10,000 to 15,000 m of drilling, citing repeated intervals of 50 to 100 m near 1 g/t Au in company drilling. The company now has 11 drill targets across 9 areas at Brewer and the adjacent Jefferson project, including Tanyard, B6 and the newly leased A1 prospect. Its best intercept to date is 62.5 m at 8.45 g/t Au and 0.28% Cu.The second path is a copper-gold porphyry at depth. A step-out hole about 1 km northwest of the former mine pierced the lithocap for the first time and returned 60 m at 681 ppm Cu and 0.24 g/t Au from 1,027 m. Croft said this proved a porphyry exists but has not located the deposit. Dr. Richard Sillitoe's review supports a tilted model, and the next deep test requires a 500 to 600 m step-out onto Jefferson ground. A second deep hole near the mine added 51.15 m at 0.62 g/t Au and 0.22% Cu outside the resource.Commercial terms improved in August 2026. The estimated US$30 million purchase price for Brewer is no longer due at closing, but after a new mine is fully permitted, payable over 10 years. Croft said the EPA indicated a financial assurance bond of about US$8 million, against about US$100 million at Haile. The option runs to the end of 2030. Croft argued that processing the backfill could also reduce the acid drainage that costs the government about US$1.3 million a year to treat, and he cited a sludge pile assaying about 0.4 g/t Au and 0.7% Cu.With C$1.5 million cash, the company runs metallurgical, physical property and age-dating work, plans to raise capital when timing improves, and is in partnership talks with larger companies. Croft is the third-largest shareholder and plans to buy more. Key risks are dilution, limited near-term news flow, the conceptual status of the porphyry and the 2030 option deadline.View Carolina Rush company profile: https://www.cruxinvestor.com/companies/carolina-rushSign up for Crux Investor: https://cruxinvestor.com/subscribe
Interview with Gavin Ferrar, CEO of Central Asia Metals PLCOur previous interview: https://www.cruxinvestor.com/posts/central-asia-metals-lsecaml-proposed-cygnus-acquisition-fills-missing-piece-in-strategy-10672Recording date: 19th November 2026Central Asia Metals (AIM, TSX:CAML) has changed from a dividend-paying base metals producer into a self-funded copper growth company. On October 27, 2026, it completed the acquisition of Cygnus Metals and its 100%-owned Chibougamau copper-gold project in Québec, and its shares began trading on the TSX the same day.The cash engine is Kounrad in Kazakhstan, an SX-EW operation that leaches historical waste dumps. 2026 guidance is 12,000-13,000t of copper cathode, and 9,758t was produced in the first nine months. First-half C1 cash cost was $0.91/lb, up from $0.79/lb because of a stronger tenge and payroll inflation. Kounrad still delivered an 84% EBITDA margin. The asset generates around 75% of group cash. Group adjusted free cash flow was $46.8M in the first half, and management points to roughly $100M a year at current prices for at least another 2-3 years. Sustaining capex is $2-3M a year, with no trucks, crushers or mill.The upside case at Kounrad is life extension. CEO Gavin Ferrar states the license runs to 2034, but dump recovery has beaten the leach curves from the original test work. Management once expected only around 1,000t/yr of copper after 2034 and now expects multiples of that. A team is defining the extension requirements, and the company is targeting an answer on the process by end-2026. The company estimates 75,400t of recoverable copper at end-2025, enough to support operations to at least 2034.Chibougamau provides the growth. The current MRE is 6.4Mt M&I at 2.3% Cu, 0.8 g/t Au and 7.6 g/t Ag, plus 8.5Mt Inferred at 2.1% Cu, 1.7 g/t Au and 7.9 g/t Ag. Corner Bay, Cedar Bay, Devlin and Golden Eye would feed the 900ktpa Copper Rand mill in a hub-and-spoke model. The mill has been idle since 2008 and needs heavy refurbishment. The deposits are steeply dipping, extend to around 1,200m depth, and suit the underground methods used at Sasa.The work programme is fully funded. Three rigs are in place by end-November and a fourth arrives in Q2 2027, for up to 70,000m of drilling through 2027. Ausenco is leading an expanded-scope PEA due mid-2027, and an updated MRE is scheduled for Q3 2027. Management is targeting a firm project view by December 2027, followed by a feasibility study. The land package covers about 18km of strike.On capital allocation, the company held $97.2M of cash at June 30, 2026, against a $0.9M overdraft. The dividend policy is 30-50% of FCF, and the first-half dividend of 8p was 40%. Cash also funds exploration in Kazakhstan and Canada, Sasa life extension and Chibougamau studies, while building a construction balance. No equity raise is planned unless a value-accretive deal requires it. Sasa is out of its turnaround, with zinc output up 9% and lead up 11% year-to-date.Learn more: https://www.cruxinvestor.com/companies/central-asia-metalsSign up for Crux Investor: https://cruxinvestor.com/subscribe
Interview with Rick Winters, CEO of Blossom GoldOur previous interview: https://www.cruxinvestor.com/posts/made-in-america-blossom-gold-tsxvbgau-visiting-the-rosebud-project-10965Recording date: 18th November 2026Blossom Gold (TSX:BGAU) is nine months into work at the Rosebud Project in Pershing County, Nevada. It has drilled about 30,000m and reopened the historic underground, and it has its first metallurgical results. The company is targeting an updated resource estimate in Q1 2027 towards construction in 2029 and production in 2030.Metallurgy is now driving the flowsheet decision. Preliminary oxide bottle rolls averaged about 73% Au recovery at a 25mm crush. Fresh rock returned around 36%. CEO Rick Winters says the weaker-leaching zones reflect liberation, possibly silica encapsulation, not refractory ore, and that historic data show these zones are discrete. They can therefore be mapped and mine-planned. Winters says even 28% fresh-rock recovery would still return roughly a 100% EBITDA margin per ton mined at current gold prices. The company is still testing whether higher-grade fresh rock earns a mill. KCA leads the heap leach and feasibility work, and McClelland Laboratories handles milling and flotation tests.Silver is the surprise. Blossom assumed 25% Ag recovery internally, and preliminary tests are averaging above 60%. In situ, Rosebud carries about 10oz Ag per oz Au. Winters estimates a silver credit at these recoveries would cover about one-third of heap leach opex. Silver is not yet in the company’s economics.Cutoff grades define two flowsheets. On a full-cost basis, the heap leach cutoff is about 0.17 g/t. The current inferred resource at that cutoff is 70.8 Mtons at 0.62 g/t Au and 6.49 g/t Ag, for 1.28 Moz Au and 13.4 Moz Ag. A CIL cutoff of about 0.4 g/t leaves about 45 Mtons at 1.1 g/t. Management describes either route as roughly a $500M project: a ~15 Mtons/yr heap leach or a 7 Mtons/yr CIL plant. Both would produce about 200,000 oz Au a year at current grades. The likely outcome is a large heap leach with a smaller mill.Drilling for the resource update has grown from 28,000m planned to 46,000m. The search radius was tightened from 220ft to 160ft. The remaining ~12,000m surface and ~8,000m underground program targets at least 70% measured and indicated. Management expects a gross resource on the order of 150 Mtons. Underground rehab is about one-third complete, and Timberline Drilling is targeting infill drilling in the first half of December. A 23,000-ton bulk sample permit and toll-milling talks offer possible early cash flow from plus-3 g/t material.While water is a main risk, Pershing County’s basin is over-allocated but under-pumped: about 32,000 AF appropriated, about 31,000 AF recharge and only about 11,000 AF pumped. Hycroft controls most mining rights. Blossom is pursuing waivers, a 275 AF purchase, state engineer applications and a possible Hycroft lease, and it expects a two-year process with protests.On valuation, Winters says peer P/NAV multiples have roughly halved since mid-2026. Blossom trades at about 0.08x NAV, around one-third of its peer average. Catalysts are column results from December, underground infill drilling, the Q1 2027 resource update and the June 2027 Plan of Operations filing.View Blossom Gold's company profile: https://www.cruxinvestor.com/companies/blossom-goldSign up for Crux Investor: https://cruxinvestor.com/subscribe
Interview with Jeremy Crozier, COO of Leviathan Metals Corp.Our previous interview: https://www.cruxinvestor.com/posts/leviathan-metals-tsxvlvx-advancing-central-copper-in-botswana-drill-assays-ahead-12427Recording date: 18th November 2026Leviathan Metals Corp. has reported the first laboratory assays from Central, its 100%-owned copper project on Botswana’s Kalahari Copper Belt (KCB). Central directly adjoins MMG’s Khoemacau group of deposits and discoveries, which MMG acquired with the nearby Banana Zone, Zone 6 and Ophion in 2023 for US$1.9 billion. According to figures Leviathan cites, the Khoemacau group holds Measured and Indicated Mineral Resources of 94 Mt at 1.8% Cu and 22 g/t Ag, plus Inferred Mineral Resources of 188 Mt at 1.6% Cu and 20 g/t Ag.Latest news release covered targeted horizons in 6 holes. At a 0.1% Cu cut-off, the best interval was 1.29 m at 0.47% Cu and 11.9 g/t Ag from 142.9 m. Other intervals included 2.3 m at 0.15% Cu from 228 m, 1.06 m at 0.2% Cu and 10.91 g/t Ag from 116.8 m, and 1.0 m at 0.1% Cu and 5 g/t Ag from 162 m. At a 0.05% Cu cut-off, the best interval widened to 2.2 m at 0.31% Cu.Leviathan interprets the results as the margins of a broader mineralizing system. The company states that at known KCB deposits, peak intersections above 0.1% Cu occur within each deposit’s mineralized envelope. At Central, the reported results fall within a geological envelope more than 4 km long near the contact between the D’Kar and Ngwako Pan Formations, where every known KCB copper deposit occurs. All but two holes show visual copper sulfides, every hole has returned portable XRF copper readings, and almost every hole has intersected the contact.Chief Operations Officer Jeremy Crozier stated three vectors point the next holes deeper. The siltstone and sandstone host package thickens along strike and appears to thicken at depth. Structural preparation, the shearing, brecciation and faulting that make rock receptive to copper, increases toward the copper. Lead and zinc form a halo around the copper, with one interval returning 0.76% Pb and 0.15% Zn alongside 0.1% Cu.First-pass holes met the contact at roughly 115-170 m from surface. The next pierce points are planned at about 200-250 m on the northwestern limb. Crozier noted that MMG’s Zone 5 extends many hundreds of meters below surface, in places to 1 km.Slightly over 7,000 m has been drilled across 26 holes within a 10,000 m program, with the 27th hole underway. Most assays remain outstanding, and quality control delays related to certified reference materials have slowed reporting. Drilling costs about $270/m from the contractor, including camp, and the current stage is scheduled to finish at the end of January 2027. Leviathan plans to add drilling capacity in 2027.Central covers more than 20 km of the target contact around the Hyena Hills dome, the next dome south of those hosting Khoemacau. The southeastern limb has been drilled only at 2 km spacing, and a hole further southwest on the northwestern limb intersected similar host rocks. Leviathan is also well advanced on a 22-23 hole uranium program targeting mineralization that continues west from Lotus Resources’ Letlhakane project.View Leviathan Metals' company profile: https://www.cruxinvestor.com/companies/leviathan-goldSign up for Crux Investor: https://cruxinvestor.com/subscribe
Interview with John Florek, President & CEO of Emperor MetalsOur previous interview: https://www.cruxinvestor.com/posts/emperor-metals-cseauoz-ai-driven-modelling-doubles-gold-resource-in-quebec-11877Recording date: 16th November 2026Emperor Metals (CSE: AUOZ) is advancing two gold projects in Quebec’s Southern Abitibi Greenstone Belt. The flagship, Duquesne West, hosts a July 2025 maiden inferred resource of 26.9 Mt grading 1.69 g/t Au for 1.46 Moz, modeled at $2,300/oz gold. The second, Lac Pelletier, is under a purchase agreement and sits about 30 km south. It holds a 1,000 tpd mining permit valid to 2030.The 2026 program at Duquesne West has finished over 20,400 m of drilling across 66 holes, and results are out for 55 of them. Emperor reported 24.8 m at 7.0 g/t Au from about 85 m vertical depth, 8.4 m at 8.7 g/t Au from about 41 m, 18.9 m at 4.0 g/t Au from about 100 m and 8.6 m at 6.1 g/t Au from about 46 m. All of these sit inside the conceptual Phase 1 pit area. President and CEO John Florek said the drilling is returning three times the thickness or grade of historical holes, and he credits AI-built 3D models that track where structures controlling the gold intersect.These results support a phased open-pit plan. Florek described starter pits about 500 m long, 200 m wide and up to 100 m deep. Management is targeting 3 to 6 g/t Au in the starter pits and roughly 2 g/t Au across an ultimate pit about 1.8 km long, 800 m wide and 400 m deep. The current pit-constrained resource grade is 1.11 g/t Au. Lower stripping ratios in the starter pits could shorten payback. Below the pit, Emperor is targeting underground grades of 4 to 6 g/t Au, and an overall 3 to 5 Moz from surface to 1,000 m depth.The project’s features favor low costs. Cyanide leach recoveries ran 90% to 94% for replacement-style ore. Sulfides are low, with no meaningful arsenic or copper. Florek said six mills are within a 30 to 40 minute drive, so Duquesne West could be developed as satellite feed. He estimated this would save $500 million to $1 billion in capital costs and said it would let the project work at $1,800 gold.Lac Pelletier offers a quicker route to production. It has 3.3 km of underground development, a historical resource of 227,000 oz at 3.9 g/t Au (not treated as current) and roughly C$70 million spent on it previously. Florek said the permitted rate could support about 40,000 oz per year. Emperor is targeting the transfer of surface-rights liabilities from Eldorado Gold in late November or early December 2026. A dewatering permit, rehabilitation and an updated NI 43-101 report follow.Upcoming catalysts are the remaining assays, 3,000 to 5,000 m of fully funded drilling, an updated Duquesne West resource targeted for the first half of 2027, and a PEA that could start around June or July 2027 and take 6 to 8 months. The main risks are that the whole resource is inferred, the starter-pit grades are targets rather than modeled figures, and both the Lac Pelletier restart and the PEA timing depend on approvals and market conditions. Florek put the market capitalization at about $77 million. Working capital was estimated at C$5.4 million as of September 2026.View Emperor Metals' company profile: https://www.cruxinvestor.com/companies/emperor-metalsSign up for Crux Investor: https://cruxinvestor.com/subscribe
loading
Comments