Transpower was warned crews needed more training before outage
Update: 2024-09-25
Description
Entirely avoidable, this is the conclusion of a report into a collapsed pylon that cut power to thousands of Northland businesses causing economic losses of up to 80 million dollars. The much anticipated Electricty Authority report, was ordered by the Energy Minister in the wake of the incident. It also found that the grid operator Transpower had been warned contractor maintenance crews needed more training but it did nothing. Northland reporter Peter de Graaf gauged the reactions from people affected by the outage.
Comments
Top Podcasts
The Best New Comedy Podcast Right Now – June 2024The Best News Podcast Right Now – June 2024The Best New Business Podcast Right Now – June 2024The Best New Sports Podcast Right Now – June 2024The Best New True Crime Podcast Right Now – June 2024The Best New Joe Rogan Experience Podcast Right Now – June 20The Best New Dan Bongino Show Podcast Right Now – June 20The Best New Mark Levin Podcast – June 2024