10/2/25 SCCRTC Part 5a - Coastal Trail Project Delivery (less long introduction)
Update: 2025-10-08
Description
The same as Part 5 but without the long introduction and project background.
Overview
- Coastal Rail Trail Segments 8-11 face significant funding and delivery challenges.
- Escalating costs and funding gaps threaten project timelines and scope.
- Multiple phasing and scope reduction options analyzed; none fully close the funding gap.
- $19.5M federal RAISE grant and $20.5M Safe Streets for All grant (pending) are key funding sources.
- Measure D sales tax is critical for leveraging state and federal funds, but is insufficient for full buildout.
- Project delivery is at risk due to strict grant deadlines and limited new funding opportunities.
Project Introduction and Recusal for Conflict of Interest
- Coastal Rail Trail Segments 8-11 project delivery discussed.
- Chair Montecito recused due to conflict of interest.
- Planning grant for Watsonville circulation pursued, supporting previous Reconnecting Communities grant application.
- Focus on future project planning in City of Watsonville.
Project Overview, Funding Success, and Challenges
- Coastal Rail Trail is a 32-mile multi-use path from Davenport to Pajaro.
- Project divided into segments; current focus on segments 8–11 (Santa Cruz to Aptos).
- Project approval and environmental phase began in 2020; construction scheduled for 2027.
- Construction expected to take 2–4 years; significant time spent on environmental review and design.
- Recent efforts focus on cost reduction and project delivery strategies due to funding shortfalls.
Cost Escalation, Funding Gaps, and Phasing Options
- Value engineering analysis and MOU with Roaring Camp completed to reduce track relocation costs.
- Secured $19.5M federal RAISE grant; City of Santa Cruz applied for $20.5M Safe Streets for All grant.
- Coastal Rail Trail segments 8–11 require additional funding for final design and construction by 2027.
- Existing grants do not cover cost increases; new state and federal funding is scarce and competitive.
- Project phasing and scope reduction options analyzed, but even minimal reductions exceed available Measure D revenues.
Financial Scenarios, Grant Assumptions, and Feasibility Analysis
- Future project phases require funding; no identified source yet.
- Assumed minimum local match is 20% of project cost; higher match increases competitiveness.
- Option C funds 1.5 of 6.5 miles with Measure D, leaving ~$20–21M for future phases or matching.
- Financial analysis excludes potential $20M Safe Streets for All grant.
- Ongoing cost tracking; current funding gap addressed via Consolidated Grant Program application, with decisions expected in November.
Distribution of Funds and Project Wrap-Up
- Majority of funds distributed to city and county of Santa Cruz.
- Significant portion allocated to corridor maintenance.
- Some funding dedicated to city of Watsonville.
- Project concept report used for trail alignment development in Watsonville.
- Regional portion of North Coast Trail under development.
Comments
In Channel




